Concrete pavement repair is continuing along Central Avenue. Work has been completed along 12th Street N and along Central Avenue from the entrance of Hanna Field north to 12th Street N. This segment of the project, along with the intersection of 6th Street N will be reopened Monday, September 16th. At that time the Contractor will be closing one lane of traffic in the intersection of Main Street and Central Avenue. Main Street traffic will be controlled with temporary traffic signals. Central Avenue will be closed to through traffic between 2nd Street S and 2nd Street N. Access to businesses in this segment will be maintained.
The installation of the new street lighting on Central Avenue will begin on Monday, September 16th. During this time segments of the parking lane will be closed to facilitate the installation.
Additional updates will be provided as needed.